Its the last week of the course~ and i just wana say THANK YOU to every member who works in Dave's house from day 1 till now and still exist lol~~ Bobby, Dolphin, Dave, Morris , Matthew and Tim. You guys been awesome and lets enjoy the last week of Unitec :)

(the photo above is for the people who left the group and bitxh away*) Eg. sonny ...

Carpentry thoughout the year 2011-9

Dave showing us how to make backing blocks.... cause he wants a LV 5 finishes??
Student screwing the board (jokes)
Dave fixing ceiling Gib, also telling us the difference between TE/SE BL1 and Aq
Insulation

Carpentry thoughout the year 2011-8

To reduce waste, we carefully mark and cut every weatherboard

Cedar weatherboard claddding~~ it was fun to paint the weatherboard too.

Carpentry thoughout the year 2011-7

Dave teaching us how to measure and cut the soffit board

Dave telling us there must be no hammer mark on the soffit board


Dave showing us how to fix building paper~

Carpentry thoughout the year 2011-6

Fixing Scaffolding: Dave is very concern about our safety, therefore we have the check the scaffold every morning before stepping on it.

we then fix roof truss

Carpentry thoughout the year 2011-5


Adjusting to wall frame, making sure is flat straight


Wall framing : Each frame was given a number, basically we just have join the wall frame according from the plan which was provide from the manufacturer .

First we located the frame to its correct position, fix two frame with a nail plate at top, adjust the frame til its plumb/ level and fix the bottom.

Carpentry thoughout the year 2011-4




Subfloor: installing foil paper and flooring, student marking the nail position on the floor. and applying adhesive between boards. Flooring must be fix within 15mins after applying adhesive.